Project time line
First interest in building a geodesic dome
<<2000
Initial research completed
Early 2001
First prototype designed
Summer 2002
We realize that the dome will exceed 15 ft height restrictions on an auxillary building
Late 2003
We realize that by joining the dome to the house through a great room, everyone gets what they want and the separate building restriction no longer applies.
June 2006
We finally get serious enough to engage architect
September 2006
Architectural plans complete
November 2007
Submit permit application: structure conforms to setback, lot coverage, and height restrictions. The plan is to start the project during Spring Break and finish it during the Summer. ("The best laid plans of mice and men...")
March 11, 2008
Layout foundation for excavation
March 17, 2008
Permit application rejected: "Holmdel doesn't allow 'home laboratories,' and why do you need such a big addition to your home, anyway?"
March 26, 2008
Engage the services of a land use lawyer who helps me realize my expert witness consulting fees aren't as outrageous as the fees a lawyer charges
April 7, 2008
Submit appeal to Zoning Board
April 17, 2008
First available zoning board meeting - "We still don't allow things called laboratories in residential lots, but it's really a home electronics workshop used for amateur radio, among other hobbies, so its OK!"
May 28, 2008
"Memorialization" of decision
June 25, 2008
Second permit application with redrawn plans eliminating any reference to forbidden evil laboratories
June 26, 2008
Building permit approved
August 15, 2008
After 5 months, layout foundation again
September 3, 2008
We finally break ground for foundation
September 5, 2008
Excavation and grading finished
September 11, 2008
Building inspector grants approval to pour footings
September 15, 2008
Footing poured
September 18, 2008
Concrete block wall finished
November 10, 2008
Prefabricated dome panels delivered
November 26, 2008
Radiant heat tubing installed in great room floor
December 5, 2008
Building inspector grants approval to backfill foundation
December 10, 2008
Building inspector grants approval to pour great room floor
December 12, 2008
Steel I-beam columns installed
December 14, 2008
Backfill complete
December 18, 2008
Elevator pit concrete poured
December 18, 2008
Great room floor poured
January 5, 2009
Radiant heat tubing installed in dome floor
January 9, 2009
Plumbing inspection of dome radiant heat tubing - cancelled by building department
January 15, 2009
Building inspector grants approval to pour dome floor
January 22, 2009
Dome floor poured
February 11, 2009
Dome assembly
May 6 - 11, 2009
Great room framed
May 25 -
June 13, 2009
....

This page was last updated on: Sunday, November 01, 2009